Deerns helped to shape a world-class experience for the Olympic Winter Games Milano Cortina 2026.
Deerns was proud to play an integral role in delivering state-of-the-art infrastructure and sustainable solutions to support the Olympic Winter Games in early 2026.
Giuseppe Dibari, Managing Director, Deerns Italy explains, “Working alongside an international team of experts, Deerns tackled the unique challenges of transforming existing sites and constructing new facilities that met the Olympics’ high standards. From the adaptive reuse of Milan’s historic venues to designing energy-efficient structures for the Olympic Village, our commitment to excellence and sustainability helped to set a new standard for temporary international events.”
Expanding the Olympic Legacy
In 2021, Deerns was commissioned to design the Olympic Village, marking the beginning of an ongoing relationship. The Fondazione Milano Cortina 2026, established to oversee the 2026 Olympics, engaged Deerns to bring sustainable engineering and modern solutions to a series of ambitious projects across Milan and Cortina. This encompassed a series of high-impact assignments:
- Olympic Village: located in the heart of Milan’s dynamic Porta Romana district, this project included the transformation of two historic structures and six new residential buildings. Hosting thousands of athletes in the short term, the Village also serves post-Olympics social goals as student housing. Deerns’ design focused on efficiency and comfort, featuring advanced mechanical, electrical, and plumbing (MEP) systems to lower energy use and minimise environmental impact. Completed in late 2022, the Village is an example of modern urban design, setting a new standard for adaptive reuse and sustainability in Olympic projects.
- Multimedia Centre: located at the former Milan Trade Fair site, this building supported journalists and broadcasters as the primary media hub for the 2026 Winter Olympics. Deerns met the demands of a continuous media environment with services such as reliable MEP systems, ICT solutions, acoustic engineering and structural improvements for operational demands. The design was finalised in September 2024, ensuring enough time for implementing a resilient media infrastructure.
- Venue Overlays: Deerns provided overlay services to adapt 19 existing venues in Milan and Cortina for the Winter Olympics. Key sites included the San Siro Olympic Stadium, Santagiulia and Rho Ice Hockey Arenas, Cortina Curling Stadium, and Tofane Alpine Skiing Centre. This project covered structural and MEP work tailored to the Olympics’ specific needs. With collaboration from Deerns’ teams across Europe, the venue overlays were delivered between April and June 2024.
- Temporary Power Management: Deerns, as the Temporary Power Manager, supervised critical power infrastructure for the games, from drafting specifications to contractor selection. This role, active from February 2024 to April 2026, ensured uninterrupted power supply across all venues, supported by careful planning and backup systems for a reliable Olympic experience.
Overcoming Challenges: A Triumph of Flexibility and Collaboration
The scale and temporary nature of the Milano Cortina Olympics posed unique challenges, requiring Deerns to innovate continuously and adapt on the fly. Deerns’ multidisciplinary approach allowed the team to meet the rigorous demands of a temporary event with precision, flexibility, and speed.
Some of the key challenges included:
- Time Constraints: The compressed timelines for both the venue overlay (April-June 2024) and the Multimedia Centre meant rapid coordination was essential. Deerns addressed this by forming a high-performing international team that could respond quickly to changing project demands.
- Stakeholder Diversity: Coordinating with a broad range of stakeholders, from local municipalities to international Olympic committees, required deft communication skills. Deerns’ project managers adapted to these complex needs, fostering collaboration across various cultural and operational perspectives.
- Existing Facility Modifications: Much of the work involved retrofitting old buildings and adapting them to Olympic requirements, particularly regarding temperature and humidity control. Deerns’ engineers worked tirelessly to achieve the ideal conditions essential for venues such as the ice skating and hockey arenas.
- Reliability and Resilience: Given the nature of the Olympics, there was no room for service disruptions. Nowhere was this more critical than in the Multimedia Centre, where communications had to be flawless throughout the games.
Here’s where we drive Olympic Innovation & Excellence
Deerns’ team members from Italy, Spain, France and The Netherlands came together to deliver innovative solutions, underscoring the company’s capacity to operate as a unified force across borders. This collaboration was instrumental in meeting project deadlines and ensuring that all services aligned with Olympic standards. Positive feedback from the Fondazione Milano Cortina 2026 and various stakeholders further highlighted Deerns’ dedication and adaptability.
Deerns was proud to contribute to a project that merges innovation, sustainability, and international cooperation – setting a new benchmark for Olympic engineering.