Borsa Istanbul (TR) – Fast-Track Delivery of Low OPEX Brownfield Data Centre


Project Details

  • 600 m2 white space
  • 1 MW IT power
  • PUE 1.35 (Annualized)
  • Turkey’s first ‘hybrid dry cooler’ implementation for low OPEX & TCO
  • Fault tolerant performance

Scope

  • Mechanical Systems
  • Electrical Systems
  • Plumbing Systems
  • (Fire) Safety & Security Systems
  • Control & Instrumentation systems
  • DCIM
  • Structured Cabling
  • Architecture
  • Structural Engineering
  • Overall Project Management

Deerns’ Services

  • Identification of Key Values
  • Concept Exploration & Conceptual Design
  • Complete Detailed Design & Tender Documentation
  • Procurement Support and Documentation
  • DCIM Design
  • Construction Supervision (QA / QC)
  • Testing and Commissioning
  • Site Management
  • Verification of all test documentation
  • Represented BORSA Istanbul during the testing and commissioning
  • Solution consultancy and implementation support
  • Testing & Commissioning management
  • QA/QC Supervision
  • Training Employees